Microsoft Walks Away From Britain's Largest AI Data Centre

Nscale was told the power for its Loughton site will not arrive until the 2030s, having expected it this year. The company filed for a US listing last month with Microsoft named in the prospectus as an expected major customer.

By
· Updated 3 min read
inLinkedIn𝕏Post
Electricity pylon at Sainsbury's Low Hall, Chingford, London, England
Electricity pylon at Sainsbury's Low Hall, Chingford, London, England · Acabashi · CC BY-SA 4.0 · via Wikimedia Commons

Microsoft has terminated its agreement to take capacity at Nscale's planned data centre in Loughton, Essex, Reuters reported on 18 October 2026, citing a Telegraph report published the same day. Microsoft was one of the two largest customers of the British cloud provider and was to be the anchor tenant at its first UK site. Microsoft declined a Reuters request for comment.

Nscale pledged £2bn last year to build the facility, which the BBC describes as the largest AI data centre in the UK and which is expected to create 250 permanent jobs when it opens. Microsoft had said it would fund a supercomputer at the site. Last month the company announced that some of the $30bn (£22bn) it is investing in the UK would pay for it.

The connection that slipped to the 2030s

The data centre was due to receive its power supply at the end of this year. Nscale has been told it will not arrive until the 2030s, the Telegraph reported first and the BBC confirmed on 18 October 2026. That is a delay measured in years, not quarters, on a site whose entire commercial case rests on energising racks before the hardware inside them is obsolete.

Nscale says it is not abandoning the project. A spokesperson told the BBC the company was exploring other ways to power the site.

We remain committed to both the Loughton project and the UK and we are exploring alternative power sources for the site, in addition to other expansion sites in the UK

— Nscale spokesperson, statement to the BBC, 18 October 2026

The company also played down the damage to its relationship with its largest customer, telling the BBC that "this unfortunate London-wide grid issue has no impact on our other contracts" and that the relationship with Microsoft "remains strong and long-term". The two are still working together on projects in Norway, Portugal and the United States.

What the prospectus promised

The timing is awkward. Nscale filed for an initial public offering in the United States last month, and its prospectus names Microsoft and Anthropic as expected major customers, according to Reuters. The Nvidia-backed company has grown from $100 million to more than $103 billion in total contracted value in two and a half years, Reuters reported, and competes with CoreWeave, Nebius, Crusoe and Lambda. It has positioned itself as Britain's sovereign data centre provider.

Contracted value is a promise, not revenue, and this is the week the distinction acquired a face. An anchor tenant walking away from the flagship domestic site, weeks before a listing that lists that tenant, is the kind of detail institutional buyers read twice.

Nscale is the second AI infrastructure business in six weeks to have a public listing complicated by investor scepticism about debt-funded compute. As Parallax Nexus reported on 12 October, Firmus shelved a $5bn Sydney float and said it would raise privately instead. The common thread is not demand for AI capacity, which nobody disputes, but the gap between contracted demand and the physical plant needed to serve it.

The honest reading is that the binding constraint on British AI capacity has stopped being capital and started being interconnection. Nscale could raise the money and sign the tenant, and still could not get electrons to Loughton inside the decade. A grid queue is a slower problem to fix than a funding round, and it is not one a prospectus can solve.

What is not established is the reason for Microsoft's exit. Reuters was explicit that the Telegraph report did not specify why the company withdrew, Microsoft has said nothing on the record, and the grid delay is a plausible cause rather than a confirmed one. Nor has anyone disclosed what the terminated agreement was worth, or whether Microsoft owes anything on cancellation.

What happens next?

  • Nscale says it is seeking alternative power for Loughton, including other UK expansion sites, with no timetable given.
  • The company's US listing will test whether public investors will fund contracted AI capacity that is not yet connected to a grid.
  • Microsoft has not explained the termination and has made no commitment about the £22bn UK investment component earmarked for the Loughton supercomputer.

Sources & references

  1. 01Microsoft pulls out of UK data center deal with Nscale, Telegraph reports — ReutersnewsWire report of 18 October 2026; source of the IPO filing, contracted value and competitor details.
  2. 02Microsoft pulls out of Nscale's Essex AI data centre — BBC NewsnewsSource of the Nscale statements, the £2bn pledge, the 250 jobs and the 2030s grid date, 18 October 2026.
  3. 03Microsoft axes AI deal in setback for UK data centre pioneer — The TelegraphnewsOriginal report by technology editor James Titcomb, 18 October 2026.
  4. 04Microsoft pulls plug on Nscale data centre deal — Financial TimesnewsIndependent confirmation of the termination, 18 October 2026.
Published 19 October 2026 · Updated 19 October 2026 · Report a correction · How we use AI
inLinkedIn𝕏Post

More from Business

View all
Business

Anthropic's S-1 Shows $16.3bn of Revenue and a $693m Loss

Anthropic's Form S-1 reports $16,286m of revenue for the first half of 2026 against $1,163m a year earlier, a $693m operating loss, and a $80,748m net loss of which $72,388m is the change in fair value of convertible notes and similar instruments. The filing leaves the price range and share count blank.

4 min read
Business

Citi Wins a China Brokerage Licence After Five Years

China's securities regulator cleared Citigroup Global Markets Holdings to establish a wholly owned brokerage in Shanghai, ending an application that had been pending since December 2021 and returning Citi to onshore securities six years after it left its Orient Citigroup joint venture.

3 min read
Business

TSMC's 2nm Ramp Took 1.3 Points Off Its Gross Margin

TSMC published its third-quarter results on 15 October 2026: revenue of $46.72 billion above its own guidance, a sixth consecutive record profit, and a gross margin of 66.4 per cent that the chief financial officer tied to the early two-nanometre ramp.

3 min read