Local Opposition Stalled $68 Billion of Data Centres in Three Months
Data Center Watch counted 45 US projects blocked or delayed between April and June 2026. In the five days to 22 September, Virginia, Texas and the Australian state of Victoria each rewrote the rules for where such sites may be built.

Forty-five US data centre projects worth $68 billion were blocked or delayed by local opposition between April and June 2026, according to a report the research group Data Center Watch published on 21 September and provided to Bloomberg News. Those 45 projects represented more than half of all new large-scale developments the group began tracking during the quarter.
The same tracker, a project of the firm 10a Labs, counted 75 disrupted cases worth roughly $130 billion in the first three months of 2026. Taken together the two quarters put close to $200 billion of proposed capacity into delay or cancellation in a single half-year. Data Center Watch also counted 843 opposition groups operating across 49 states, with Hawaii the only exception, and said some 30 statehouses have introduced or adopted rules covering data centre siting, electricity or water.
New groups continue to emerge, opposition is appearing across a wide range of states and jurisdictions, and online petition signatures continue to grow
One petition against a project in Tennessee gathered more than 500,000 signatures on Change.org during the quarter, which Data Center Watch said accounted for more than a third of all signatures collected on that platform in the period.
What Virginia stopped paying for
Governor Abigail Spanberger signed Executive Order 22 in Richmond on 18 September 2026. With immediate effect, the Virginia Economic Development Partnership may no longer assist new data centre projects with anticipated peak electrical demand of 25 MW or more through the Virginia Business Ready Sites Program, expedited permitting or similar discretionary programmes. The order also bars executive-branch agencies from entering into or requiring non-disclosure agreements on data centre projects, directs the Department of Environmental Quality to deliver a study of the cumulative emissions from data centre backup diesel generators by 17 March 2027, and creates a state AI task force covering workforce displacement, privacy and cybersecurity.
Starting today, this industry won't have carte blanche to play by their own rules in Virginia
The sharper measures are not yet law. Spanberger's wider Data Center Accountability Framework proposes ending by-right approval and requiring local government sign-off for any data centre drawing more than 25 MW, and that requires the General Assembly, which returns in January 2027. The Data Center Coalition, the industry's trade body, said on 18 September that it shares the governor's goals but warned that significant and abrupt policy changes could jeopardise jobs and investment.
Texas widens a pause it already had
Three days later, on Monday 21 September, Governor Greg Abbott ordered the Texas Commission on Environmental Quality to halt all data-centre-related permits until ERCOT completes an audit of the waitlist of projects seeking grid connection. Abbott's office had ordered that audit in August alongside a moratorium on new grid approvals; the new directive extends the freeze from electrical approvals to environmental ones. TCEQ is to report on its compliance by 19 October. The August moratorium announcement said Abbott would work with the Legislature next session to eliminate any financial incentives for data centres.
The sums involved are large. Analysts at BloombergNEF found in August 2026 that almost 20% of the 253 GW US data centre pipeline, close to 50 GW, was at risk from the Texas pause, with up to $8 billion in data centre revenue losses by the first quarter of 2027. JLL reported in February 2026 that Texas was on course to overtake Virginia as the world's largest data centre market by the end of the decade. Parallax Nexus has tracked the other end of the same pipe, an ERCOT large-load queue of roughly 470 GW of requests against single-digit gigawatts actually drawing power.
Politics is doing the arithmetic too. A recent NBC News poll cited by CNBC found 64% of Americans would be less likely to vote for a candidate who supports building local data centres. Abbott is running a close race for a fourth term, and in 2025 he described Texas as the coming epicentre of AI development.
The pattern leaves the United States
On Tuesday 22 September the Australian state of Victoria, home to Melbourne, announced that data centres will be banned from residential areas with a mandatory 150 metre buffer from any house. Premier Ben Carroll's rules require operators to match new energy demand with additional generation and to pay for network upgrades, and to cool their sites using only recycled or non-drinking water. Westpac has estimated the Australian data centre spending surge at up to A$225 billion, roughly $160 billion, with most of it in the next three years. Data Center Watch reported on protests outside the United States for the first time in the two years it has run the research, covering campaigns in European countries, Australia and South Africa.
As with many other trends, the US has generally been at the forefront, but the phenomenon is increasingly becoming global
The honest reading is that the binding constraint on AI capacity has moved again. Last year it was chips, then it was interconnection queues and transformers. What Virginia and Texas did in the same week is different in kind: both removed state help that developers had treated as automatic, and neither action requires a single new megawatt of generation to be found or refused. Permitting discretion is cheaper for a governor to withdraw than power is to build, and it takes effect on the day of signature.
What the figures cannot settle is how much of this is opposition and how much is a slower pipeline. Data Center Watch's project values are drawn from developers' own announcements rather than audited filings, and the swing from $130 billion in the first quarter to $68 billion in the second is large enough that fewer proposals, not weaker resistance, could explain much of it. The group does not publish a denominator for the earlier quarter comparable to the one it gives for the second.
Two dates now matter more than the totals. TCEQ owes Abbott's office an update by 19 October, three weeks before the November midterms. Virginia's General Assembly convenes in January, and only then will it be clear whether the 25 MW threshold becomes state law or stays an executive preference that a later governor can reverse.
What happens next?
- TCEQ must report to Governor Abbott's office by 19 October 2026 on its compliance with the Texas permit halt.
- Virginia's General Assembly convenes in January 2027 to consider writing the 25 MW local-approval threshold into law.
- Virginia's Department of Environmental Quality owes a cumulative backup-generator emissions study by 17 March 2027.
- Data Center Watch's next quarterly count will show whether the second-quarter fall reflects weaker opposition or fewer proposals.
Related topics
Sources & references
- 01New Data Centers Worth $68 Billion Disrupted in US, Data Show — Bloombergnews21 September 2026; Data Center Watch report provided to Bloomberg News
- 02Q1 2026 report — Data Center WatchdataFirst-quarter 2026 count of 75 disrupted projects worth roughly $130 billion
- 03New Data Centers Worth $68 Billion Disrupted in US, Data Show — Insurance Journal (Bloomberg syndication)news21 September 2026; full Bloomberg text with Miquel Vila quotes
- 04Texas Gov. Abbott orders data center permit halt weeks after issuing moratorium — CNBCnews21 September 2026; TCEQ directive, BloombergNEF and NBC News poll figures
- 05Governor Spanberger Unveils Nation's Most Comprehensive & Aggressive Data Center Accountability Standards, Signs Executive Order to Immediately Put Into Action — Office of the Governor of Virginiaprimary18 September 2026 press release
- 06Virginia moves to give communities more say on data centers — Axios Richmondnews21 September 2026; Data Center Coalition response
- 07Gov. Spanberger Moves to Rein In Virginia's Data Center Boom Without a Moratorium — Broadband Breakfastnews23 September 2026; Spanberger remarks at the 18 September Richmond press conference
- 08Australian State Bans Data Centers From Residential Areas — Insurance Journal (Bloomberg syndication)news22 September 2026; Victoria rules and Westpac estimate
More from Business
Four AI Subscribers Sue the Labs Over a Public Slowdown Pact
Four paying subscribers filed a Sherman Act class action against Anthropic, OpenAI, SpaceXAI and Google in the Northern District of California on 18 September 2026, alleging the four agreed to slow the rate at which they improve competing AI products. Every fact pleaded comes from a public statement or a press report.
Nscale’s IPO Filing Shows $103 Billion Booked and 25,000 GPUs Live
Nscale filed for a New York Stock Exchange listing on 18 September 2026. Its S-1 reports $140.6 million of first-half revenue, a $1.02 billion net loss, more than $103 billion of contracted value led by Microsoft and Anthropic, and about 25,000 of 461,000 contracted GPUs live at the end of August.
Cohere Signs for Aleph Alpha as Schwarz Group Puts In €500 Million
Cohere and Aleph Alpha signed a definitive merger agreement on 16 September 2026. The combined company will trade as Cohere, with headquarters in Toronto and Berlin and more than 1,000 staff. Reuters reports that Schwarz Group is investing €500 million. The deal still needs regulatory approval.
The Licence-and-Hire Playbook Meets the Justice Department
The US Justice Department is investigating whether Nvidia's December 2025 licensing deal with Groq, in which Groq's founder and executives joined Nvidia while the company stayed nominally independent, was structured to evade antitrust scrutiny, according to the New York Times, Reuters and Bloomberg. Two senators had already called the deal an evasion in March.