Brussels Proposes A-to-G Energy Labels for Large Data Centres
The European Commission's data centre package, published on 21 September 2026, would grade every site above 500 kW on power and water efficiency. A separate consultation on minimum standards that could rule technologies out closes on 14 December.

The European Commission proposed on 21 September 2026 a common EU rating scheme that would give every data centre above 500 kW of capacity an electronic label grading its energy efficiency, its water efficiency, where its electricity comes from and how it behaves towards the grid. The scheme arrives as a delegated regulation supplementing the recast Energy Efficiency Directive and amending the Commission's 2024 regulation that created the European database on data centres.
It is one of three pieces published the same day as the Data Centre Energy Efficiency Package. The others are a report to the European Parliament and the Council assessing what operators have reported so far, and a call for evidence on minimum performance standards, which the Commission's Directorate-General for Energy says runs 12 weeks and closes on 14 December 2026.
The database writes the label, not the operator
No new filing is involved. Under the regulation, the European database generates an electronic label automatically for each data centre that has submitted its information and key performance indicators, by 15 August 2027 and every year after that. Each label runs from 15 August of its issue year to 15 August of the next and is published in all official EU languages. Because the indicators come from reporting operators already do under the 2024 scheme, the Commission says the system creates no additional administrative burden. The database has been running since September 2024, with reporting rounds completed in 2024 and 2025.
Energy efficiency is graded A to G on Power Usage Effectiveness, the ratio of a facility's total electricity draw to the electricity reaching the computing equipment itself. Class A means a PUE of 1.15 or less; class G means anything above 1.9. Water efficiency is graded the same way on Water Usage Effectiveness, from class A at 0.1 or below to class G above 1.0. Alongside the two grades, each label carries the site's name, operator, location, size category and date of entry into operation, a QR code linking to its database entry, a breakdown of energy sourcing across on-site renewable and nuclear generation, power purchase agreements, guarantees of origin and unspecified sources, cooling degree days, whether the facility offers flexibility to the grid, and whether it is "waste heat reuse ready".
One definition will do more work than either grade. A data centre counts as contributing new clean generating capacity only where its power purchase agreements are with renewable or nuclear plants no more than ten years old, or substantially refurbished within the past ten years. That is the line between paying for electricity that already existed and paying for electricity that would not exist otherwise.
Tripling our data centre capacity cannot mean tripling the pressure on our grids, our water and our energy bills.
The rules with teeth are still a year away
A label describes; it does not forbid. The Energy Efficiency Directive gives the Commission power to propose minimum performance standards for data centres, and the consultation launched the same day is the preparatory work for exactly that, with a legislative proposal planned for the second quarter of 2027. The Commission has not said what those standards would require or which technologies they would phase out.
Getting even this far took longer than Brussels wanted. The Register reported on 22 September that the original A-to-G plan was delayed after industry criticism, that Moody's had warned grades could affect financing and collateral requirements rather than merely embarrass operators, and that a provision requiring clean-energy certificates to come from the same region as the data centre was loosened in a revised draft to allow sourcing from anywhere in the EU. A certificate bought in one member state does nothing for a strained grid in another.
The honest reading is that transparency will move money before it moves a single cooling system. Operators facing a public class F on water in a water-stressed region will hear about it from lenders and enterprise buyers well before any minimum standard exists to force a change. The strongest argument against reading too much into the grades is one the Commission concedes by shipping a contextualising document with every label: PUE tracks local climate, and WUE means something different in Ireland than in Spain, so a poor letter is not always a poorly run building.
What happens next?
- The call for evidence on minimum performance standards closes on 14 December 2026.
- A legislative proposal on minimum standards is planned for the second quarter of 2027.
- The first automatically generated labels are due by 15 August 2027, drawn from reporting already held in the European database on data centres.
- The delegated regulation is subject to scrutiny by the European Parliament and the Council before it applies.
Related topics
Sources & references
- 01Minimum performance standards for data centres in Europe: public consultation launched — European Commission, Directorate-General for Energyprimary21 September 2026. Confirms the 12-week consultation, the 14 December 2026 deadline, the Q2 2027 legislative proposal and the same-day publication of the Data Centre Energy Efficiency Package.
- 02DG Energy news: Commission enhances energy efficiency and sustainability of data centres in the EU — European Commission, Directorate-General for EnergyprimaryPress release dated 21 September 2026, listed in the DG Energy news index: the Commission 'proposed today a common rating scheme for data centres'.
- 03Proposed EU Scheme Would Auto-Generate Sustainability Labels From 2027 — Unite.AInews21 September 2026. Detailed reading of the delegated regulation's annexes and the Commission's questions-and-answers document, including the PUE and WUE class boundaries and the ten-year clean energy test.
- 04EU datacenter green scorecard finally escapes Brussels — The Registernews22 September 2026. Source for the scheme's delays, the Moody's warning on financing, and the loosening of the same-region clean-energy certificate provision.
More from Energy
DOE Renews Indiana Coal Orders Days After a Court Struck One Down
The US Department of Energy issued fresh section 202(c) emergency orders on 19 September 2026 keeping two Indiana coal stations available through 18 December, eight days after a federal appeals court ruled the same authority had been used unlawfully to keep a Michigan coal plant running.
Ofgem Moves to Charge Batteries for Holding Grid Slots
Ofgem said on 17 September 2026 it is minded to approve CMP470, a code modification raised by developer Field Energy that would make battery projects post financial security of £3,000 to £25,000 per megawatt to keep a connection slot while the queue is oversubscribed.
Iowa Got a Nuclear Restart Loan and a Data-Centre Freeze in the Same Week
On 8 September 2026 the US Department of Energy's Office of Energy Dominance Financing announced financial close on a loan of up to $1.9 billion to NextEra Energy for the restart of Iowa's only nuclear plant, targeted for the first quarter of 2029 and backed by a 25-year power agreement with Google. The same day, Waterloo's city council approved a 90-day moratorium on new data centres, joining a growing list of Iowa communities pausing projects.
Record Power Demand, Even After Texas Hit Pause
EIA's September Short-Term Energy Outlook projects US generation rising 2.2% to a record 4,368 billion kWh in 2026 and a further 1.7% in 2027, with the West South Central region the largest contributor despite the Texas pause. EIA cut its 2027 Texas load-growth forecast from 14% to 6% after Governor Abbott ordered an audit of every data centre in ERCOT's queue.