Dominion's Data Centre Queue Reached 54.9GW as Construction Fell
Dominion Energy Virginia disclosed 54.9 gigawatts of contracted data centre capacity in September 2026, up 6.3GW on December 2025. Construction authorisations inside that total fell by 1.2GW, and engineering letters supplied five sixths of the growth.

Dominion Energy Virginia held about 54.9 gigawatts of contracted data centre capacity in September 2026, up roughly 6.3GW or 13 per cent on December 2025, according to the earnings slides the company published on 30 October 2026. The composition of that increase is more interesting than its size.
Dominion sorts the pipeline into three stages, and they commit the customer to very different things. An engineering letter of authorisation buys a detailed engineering plan, with the costs reimbursed to Dominion. A construction letter of authorisation authorises construction and, in the company's own words, means the customer must reimburse Dominion Energy for all spent costs should they walk away. An electric service agreement defines how the customer will take service and includes a revenue requirement whether the customer takes service or not.
Where the 6.3 gigawatts went
Dominion Energy Virginia contracted data centre capacity by contract stage. Electric service agreement: July 2023 5.8GW, December 2025 10.2GW, September 2026 12.2GW. Construction letter of authorisation: July 2023 2GW, December 2025 11GW, September 2026 9.8GW. Engineering letter of authorisation: July 2023 8.7GW, December 2025 27.4GW, September 2026 32.8GW.
Between December 2025 and September 2026 the engineering stage grew from 27.4GW to 32.8GW and the electric service agreements from 10.2GW to 12.2GW. The construction stage fell, from 11.0GW to 9.8GW. Of the 6.3GW of net growth, 5.4GW landed in the least binding category.
A 1.2GW fall in construction authorisations alongside a 2.0GW rise in service agreements is consistent with projects graduating from one stage to the next, which would be the benign reading and is probably the right one. The slides do not say. Dominion published the stage totals and not the movements between them, so the arithmetic is as far as the disclosure goes, and whether any project left the queue altogether cannot be read off these numbers.
What the pipeline is already delivering
The demand is not hypothetical at the meter. Weather-normal regulated electric sales rose 3.4 per cent over the latest twelve months, led by commercial sales up 8.6 per cent. Dominion Energy Virginia booked $4,218m of revenue in the quarter against $3,311m a year earlier, and operating earnings of $862m against $679m. Group operating earnings were $1.28 a share, including five cents from renewable natural gas tax credits and five cents from better than normal weather, and the company said it expects to finish in the top half of its $3.45 to $3.69 full-year range.
Scale is the other half of the point. The firmest 12.2GW on its own is about three quarters of what the entire pipeline held in July 2023, when the total across all three stages was roughly 16.5GW. The queue has more than tripled in a little over three years, and the part of it that Dominion can bill regardless of whether a server ever switches on has roughly doubled.
The gap between a signed pipeline and a built one is where this gets decided, and it has already bitten elsewhere. As Parallax Nexus reported, Microsoft terminated its agreement at Nscale's data centre in Loughton, Essex, after the grid connection slipped into the 2030s, and NERC's package of new reliability standards for data centres and AI facilities cleared its final stakeholder ballot in October before heading to federal regulators.
The rules now being written around the queue
Dominion sits inside PJM, the grid operator whose territory covers northern Virginia. On 9 October 2026, in docket ER26-3515, the Federal Energy Regulatory Commission accepted PJM's definition of a large load and its large load registry, effective 12 October, and rejected the rest of PJM's proposal, including the interim resource adequacy service and the bring your own new capacity rules, as documented by RMI. The accepted definition captures any end-use customer load with a cumulative peak of 50MW or more at a single electrical site, and counts affiliated facilities within a one-mile radius as one site. Dominion's 54.9GW is the sort of thing those rules now have to measure.
One more thing hangs over the figures. Management told the earnings call that evidentiary hearings on the proposed combination with NextEra Energy begin in late 2026 and early 2027. Whoever ends up owning the queue inherits the obligation to build for it.
The honest reading is that the headline 13 per cent is a weaker signal than it looks and the 54.9GW total is a stronger one. Growth concentrated in engineering letters is growth in optionality: developers paying to find out what a connection would cost, which is cheap next to building one. The line to watch next quarter is the electric service agreement total, because that is the one Dominion collects on whether the data centre ever draws power.
What happens next?
- Dominion's next quarterly disclosure will show whether the construction stage keeps falling or recovers as engineering letters convert.
- PJM owed FERC a compliance filing within 30 days of the 9 October order on its large load proposal.
- Evidentiary hearings on the proposed NextEra Energy combination are scheduled for late 2026 and early 2027.
- NERC's new reliability standards for large computational loads go to FERC, which had ordered them filed by 31 December 2026.
Related topics
Sources & references
- 01Third-quarter 2026 earnings call slides — Dominion EnergyprimaryPublished 30 October 2026. Source for the three-stage contracted capacity figures at July 2023, December 2025 and September 2026, and for the stage definitions quoted.
- 02Dominion Energy Announces Third-Quarter 2026 Results — Dominion EnergyprimaryFurnished to the SEC on Form 8-K, 30 October 2026. GAAP earnings of $1.30 and operating earnings of $1.28 a share.
- 03Dominion's Contracted Data-Center Capacity Climbs to Nearly 55 GW as Q3 Beats — Benzinganews30 October 2026. Independent confirmation of the 54.9GW total, the 6.3GW increase and the Virginia segment revenue and earnings figures.
- 04Dominion Energy's Q3 Earnings Top Estimates, Revenues Increase Y/Y — Zacks Equity Research, via Yahoo FinancenewsIndependent confirmation of the September 2026 split of 12.2GW, 9.8GW and 32.8GW and the 8.6 per cent commercial sales growth.
- 05Scaling Markets for Distributed Energy Resources — RMIreportFootnotes FERC's order in docket ER26-3515-000, 9 October 2026, accepting PJM's large load definition and registry and rejecting the interim resource adequacy service and bring your own new capacity rules.
- 06Dominion Energy (D) Q3 2026 Earnings Call Transcript — The Motley Foolinterview30 October 2026 call. Source for the composition of quarterly operating earnings and the NextEra Energy hearing schedule.
More from Energy
Wind Turbine Imports Ruled a Security Threat With No Tariff
A section 232 proclamation published on 28 October 2026 found that imported wind turbines and their parts threaten to impair United States national security, but imposed no new tariff and instead directed Commerce and the US Trade Representative to negotiate with trading partners.
EQT Buys Range Resources to Pass 9 Bcfe a Day in Appalachia
EQT and Range Resources agreed on 26 October 2026 to an all-stock merger at 0.987 EQT shares per Range share, leaving EQT holders with about 73 per cent of a company producing more than 9 Bcfe a day. Closing is expected in the first quarter of 2027, subject to regulatory clearances and shareholder votes.
Power Poles in Melbourne Cost NextDC A$140m of FY27 Revenue
NEXTDC cut FY27 net revenue guidance to A$475m to A$500m from A$615m to A$640m on 21 October 2026 after its electricity distributor suspended network works. Shares fell 42 per cent the same day, their lowest since 2018.
Amazon Funds a 960MW Reactor Study at an Indiana Coal Site
AEP agreed on 19 October 2026 to study 960 megawatts of small modular reactors at a retired Indiana coal site, with Amazon funding development and contracting for the power. There is no final investment decision, no disclosed cost and no in-service date.