Power Poles in Melbourne Cost NextDC A$140m of FY27 Revenue

Jemena suspended parts of the 66kV works feeding NextDC's M3 campus in September after community opposition, and does not expect to restart before February 2027. The next increase in grid supply has slipped to the 2028 financial year.

By
· Updated 3 min read
inLinkedIn𝕏Post
West Footscray railway station, Platform 1, eastern view, 19 June 2026
West Footscray railway station, Platform 1, eastern view, 19 June 2026 · PEPSI697 · CC BY-SA 4.0 · via Wikimedia Commons

A suspended power pole replacement in Melbourne's inner west has taken about A$140 million out of NEXTDC's forecast revenue for the 2027 financial year. The ASX-listed operator told the exchange on 21 October 2026 that Jemena Electricity Networks had suspended parts of the 66kV line augmentation works that feed its M3 Melbourne data centre, and that the next increase in grid supply to the site is now expected in FY28, deferring the delivery and billing of contracted capacity with it.

Jemena suspended the works in September 2026 and has since formally notified NEXTDC that it does not expect to recommence them before February 2027. The release says Jemena attributed the suspension to safety concerns and lack of access to work sites arising from community and stakeholder opposition to the works, and to the local council, as the relevant road authority, not giving its consent while further community consultation takes place.

The August guidance included approximately A$140 million of each of net revenue and Underlying EBITDA from those contracts. The timing and scale of their contribution remain uncertain.

— Craig Scroggie, Chief executive officer and managing director, NEXTDC

What came out of the guidance

Source: NEXTDC Limited ASX release, M3 Melbourne Power Delay and Revised FY27 Guidance, 21 October 2026. The revised capital expenditure range includes about A$230 million of capitalised interest that the previous guidance did not.
FY27 measureGuidance of 27 August 2026Revised 21 October 2026
Net revenueA$615m to A$640mA$475m to A$500m
Underlying EBITDAA$385m to A$410mA$245m to A$265m
Capital expenditureA$5,250m to A$5,750mA$4,500m to A$5,000m

The revised revenue and earnings ranges exclude the affected M3 contracts entirely, including capacity already billing, because while parts of Jemena's works are suspended the existing grid supply cannot be relied on to support the full contracted power ramp in data halls already delivered. On capital expenditure, stripping out the capitalised interest that the new range includes and the old one did not, the like-for-like reduction is about A$980 million, or 17 to 19 per cent.

Shares closed 41.7 per cent lower at A$5.35 on Wednesday 21 October, their lowest level since 2018. The Australian Financial Review reported on 22 October that the fall wiped almost A$3 billion off NEXTDC's market value, and that some investors were questioning a month-long delay in disclosing that the power works were in trouble.

A planning decision now stuck behind an election

The grid is not the only queue. The Victorian government's decision on a planning permit for M3 Stages 6 and 7, application PA2604231, lodged in February 2026 under the state's Development Facilitation Program, is taking longer than NEXTDC expected. The government becomes subject to caretaker conventions from 3 November 2026 ahead of the state election on 28 November, and the company now expects no decision until 2027. Later increases in supply also depend on upstream work to install new transformers at the Brooklyn Terminal Station, the first of which NEXTDC now expects later than planned.

The contracts and the covenants

The deferred capacity remains under contract, subject to the customer's rights. Those contracts provide for service level credits where capacity is delivered late or is not fully powered and, in some circumstances, give the customer rights to terminate; NEXTDC said it is considering whether relief is available to it under the force majeure provisions. The company had A$8,675 million of liquidity at 30 September 2026, comprising A$1,275 million of cash, A$6,700 million of undrawn senior debt facilities and a A$700 million committed hybrid tranche, and said it remains in compliance with its covenants. It also said its ability to draw those senior facilities depends on expected customer billing profiles, and that delays to grid supply at M3 could be a material change to them.

The board has put all new development projects and land acquisitions on hold, and will announce the outcome of a capital expenditure review by the annual general meeting on 20 November 2026. It will also evaluate capital recycling, including the potential sale of development sites not required in the near term.

None of this is a demand problem. Construction of the M3 data halls is continuing inside the existing buildings and the capacity is contracted. The honest reading is that the binding constraint on AI infrastructure has moved again, from chips to generation and now to the last few kilometres of distribution network and the residents who live beside it, a pattern Parallax Nexus traced through FERC's rejection of PJM's large-load plan and Microsoft's exit from Loughton. What is not known is whether the customer will exercise any of its rights, or what the delay does to the fair value of NEXTDC's investment properties, which the company says it has not yet quantified and will reflect in its half-year results to 31 December 2026.

What happens next?

  • Jemena is consulting the community and seeking the approvals it needs to recommence the 66kV works safely, with no restart expected before February 2027.
  • NEXTDC will announce the outcome of its capital expenditure review by its annual general meeting on 20 November 2026.
  • The Victorian planning decision on M3 Stages 6 and 7 is not expected until 2027, after the 28 November state election.
  • NEXTDC will quantify the effect on investment property fair value in its results for the half year ending 31 December 2026.

Sources & references

  1. 01NEXTDC Limited: M3 Melbourne Power Delay and Revised FY27 Guidance — NEXTDC Limited via EQS NewsprimaryASX release dated 21 October 2026; source of all guidance, liquidity, covenant and contract figures.
  2. 02NextDC draws investor ire over slow disclosure of power delays — Australian Financial ReviewnewsPublished 22 October 2026; share price fall and investor response.
  3. 03NextDC cuts FY27 guidance, pauses new projects over M3 power delay — W.MedianewsTrade coverage of the 21 October 2026 ASX announcement.
  4. 04NextDC loses 42% in a day — CapacitynewsPublished 23 October 2026; closing price of A$5.35 and background on the Yarraville pole works.
Published 24 October 2026 · Updated 24 October 2026 · Report a correction · How we use AI
inLinkedIn𝕏Post

More from Energy

View all
Energy

EQT Buys Range Resources to Pass 9 Bcfe a Day in Appalachia

EQT and Range Resources agreed on 26 October 2026 to an all-stock merger at 0.987 EQT shares per Range share, leaving EQT holders with about 73 per cent of a company producing more than 9 Bcfe a day. Closing is expected in the first quarter of 2027, subject to regulatory clearances and shareholder votes.

3 min read
Energy

Amazon Funds a 960MW Reactor Study at an Indiana Coal Site

AEP agreed on 19 October 2026 to study 960 megawatts of small modular reactors at a retired Indiana coal site, with Amazon funding development and contracting for the power. There is no final investment decision, no disclosed cost and no in-service date.

3 min read
Energy

NERC Grid Rules Clear Ballot With 36-Month Recorder Delay

NERC announced on 15 October 2026 that Project 2026-02, a package of three new reliability standards for data centres, AI facilities and cryptocurrency mines, had passed its final stakeholder ballot. It now goes to NERC's Board of Trustees and then to FERC, which ordered the standards filed by 31 December 2026.

3 min read
Energy

DOE Clears PJM Plants to Exceed Emissions Limits to 16 October

Energy Secretary Chris Wright signed Order No. 202-26-50 on 12 October 2026, letting PJM run named units past their environmental permit limits and direct data centres onto backup generation before firm load shedding. It expires on 16 October.

3 min read