FERC Rejects the Core of PJM's Data Centre Connection Plan
The commission threw out PJM's Interim Resource Adequacy Service and its bring-your-own-capacity rules on 9 October 2026, keeping only a 50 MW definition and a registry. It told the states to decide who gets switched off first.

The Federal Energy Regulatory Commission on Friday 9 October 2026 rejected most of PJM Interconnection's plan for bringing data centres and other large electricity users onto the largest US grid. The order, filed in docket ER26-3515 under eLibrary accession 20261009-3055, throws out the Interim Resource Adequacy Service that formed the core of the package, along with PJM's rules for loads that bring their own new capacity.
The rejected service, known as IRAS, would have let a new large load connect before matching new generation existed, in exchange for agreeing to be curtailed ahead of other demand response in the run-up to a grid emergency. FERC accepted two pieces of the filing: PJM's definition of a large load, which keeps a 50 MW threshold, and a large load registry recording a facility's location, ramp schedule and capacity supply.
A jurisdictional problem, not an engineering one
FERC did not reject IRAS on reliability grounds. It found that the proposed tariff reached into territory the states control, because the large loads in question are overwhelmingly retail customers.
We find that several provisions of the proposed tariff appear to place obligations directly on eligible new large loads, which are, for the most part, retail customers; that certain other provisions appear to dictate which retail customers taking retail service will be curtailed; and that the proposed compensation framework appears to establish a retail rate
The commission described large-load rules as shared work with the states, said states have a central part to play in designating which retail customers must be curtailed when the system is stressed, and encouraged them to continue that work. Commissioner David Rosner, concurring, went further and flagged what PJM's proposal would have done to the capacity market, because IRAS loads would have sat outside the auction demand curve.
The result could be a capacity market signaling that PJM has more than enough capacity while the region sheds thousands of megawatts of demand on an involuntary basis. That's not only economically inefficient, but also likely to prevent supply and demand from coming back into balance.
Rosner added that in a grid emergency non-critical data centres should be switched off before homes, hospitals and schools, but that states, not the grid operator, should set those priorities, and only after voluntary demand response has been exhausted.
The second PJM rejection in six weeks
This is the second PJM data centre proposal FERC has sent back since late September. On 29 September the commission accepted but suspended PJM's reliability backstop procurement in docket ER26-3380, setting cost allocation, transmission owner exit rules and load-serving entity collateral for a paper hearing, and PJM put the 6.8 GW procurement on hold. The US Department of Energy intervened in that docket on 7 October to argue that large loads rather than households must fund the generation they require, as Parallax Nexus reported on 9 October. PJM plans to refile by 29 October and holds a special Members Committee meeting on 22 October.
Jeffrey Shields, a PJM spokesman, told Utility Dive by email on Monday 12 October that the grid operator is reviewing the order with an eye to meeting FERC's requirements while recognising the responsibilities the commission assigned to the states. Equity analysts at Jefferies told clients the same day that the ruling points to higher capacity prices for longer in PJM, which favours independent power producers including Constellation Energy, NRG Energy, Talen Energy and Vistra.
The judgment worth owning here is that FERC has now twice told PJM the same thing in different words: deciding who gets switched off, and who pays for the power, is not the grid operator's call to make alone. That moves the next step to utility commissions across a footprint PJM runs from Illinois to Washington, DC, each on its own timetable, and whether any of them will act fast enough to matter is not known. PJM filed the package on 13 August and asked for it to take effect on 12 October, according to MGRID's review of the docket, with IRAS applying to large loads entering service after 1 June 2027.
What happens next?
- PJM plans to submit a revised reliability backstop procurement filing to FERC by 29 October 2026.
- PJM holds a special Members Committee meeting on 22 October 2026 to consult members on that filing.
- PJM has not said whether it will seek rehearing of the 9 October order or refile the large-load package.
- Jefferies expects any revival of the curtailment-for-access trade to come from state regulators, with Ohio and Pennsylvania the first to watch.
Related topics
Sources & references
- 01Order on PJM large load interconnection proposal, Docket ER26-3515-000 — FERC eLibraryprimaryIssued 9 October 2026; accession number 20261009-3055; source of the commission's quoted findings
- 02FERC rejects most of PJM's large load interconnection plan — Utility DivenewsReport by Ethan Howland, 12 October 2026, carrying the PJM statement, the Rosner concurrence and the Jefferies client note
- 03FERC Rejects PJM's Curtail-First Plan for New Large Loads, and Keeps Only the 50 MW Definition and a Registry — MGRIDreportDocket review published 10 October 2026, for the 13 August filing date and the 1 June 2027 applicability
- 04FERC Rejects PJM Interim Resource Adequacy Service Proposal — RTO InsidernewsTrade coverage of the same order, October 2026
More from Energy
EQT Buys Range Resources to Pass 9 Bcfe a Day in Appalachia
EQT and Range Resources agreed on 26 October 2026 to an all-stock merger at 0.987 EQT shares per Range share, leaving EQT holders with about 73 per cent of a company producing more than 9 Bcfe a day. Closing is expected in the first quarter of 2027, subject to regulatory clearances and shareholder votes.
Power Poles in Melbourne Cost NextDC A$140m of FY27 Revenue
NEXTDC cut FY27 net revenue guidance to A$475m to A$500m from A$615m to A$640m on 21 October 2026 after its electricity distributor suspended network works. Shares fell 42 per cent the same day, their lowest since 2018.
Amazon Funds a 960MW Reactor Study at an Indiana Coal Site
AEP agreed on 19 October 2026 to study 960 megawatts of small modular reactors at a retired Indiana coal site, with Amazon funding development and contracting for the power. There is no final investment decision, no disclosed cost and no in-service date.
NERC Grid Rules Clear Ballot With 36-Month Recorder Delay
NERC announced on 15 October 2026 that Project 2026-02, a package of three new reliability standards for data centres, AI facilities and cryptocurrency mines, had passed its final stakeholder ballot. It now goes to NERC's Board of Trustees and then to FERC, which ordered the standards filed by 31 December 2026.