DOE Tells PJM to Fix Data Centre Cost Allocation by 29 October

The Department of Energy filed a statement of position at the Federal Energy Regulatory Commission on 7 October 2026 backing the regulator's finding that PJM's cost allocation model may be unjust and unreasonable. PJM says it will file revisions rather than wait out a five-month hearing.

By
· Updated 3 min read
inLinkedIn𝕏Post
Arlington substation
Arlington substation · U.S. Department of Energy · CC0 1.0 · via Wikimedia Commons

The US Department of Energy filed a statement of position at the Federal Energy Regulatory Commission on Wednesday 7 October 2026, asking PJM Interconnection to rewrite the part of its capacity procurement plan that decides who pays for power built to serve data centres. The filing lands in docket ER26-3380 and supports the regulator's own conclusions against the grid operator that submitted the plan.

PJM should implement the cost allocation and other reforms identified by the Commission to ensure that the costs of serving new data centers or other large electric energy loads are not unfairly shifted to PJM's existing ratepayers

— US Department of Energy, statement of position filed at FERC, 7 October 2026

What FERC stopped on 29 September

PJM proposed the Reliability Backstop Procurement in a tariff filing on 31 July 2026, a one-time purchase of new capacity meant to close a shortfall largely driven by data centre demand forecasts. FERC accepted the framework on 29 September but suspended it for five months, to an effective date of 28 February 2027 and subject to refund, and opened a hearing. The commission preliminarily found three elements may be unjust and unreasonable: the cost allocation method, the rules letting transmission owners exit, and the collateral load-serving entities must post.

The effect was immediate: PJM had planned to open the procurement on 30 September and did not. It is seeking about 6.8 GW of new capacity to cover the shortfall from the 2028/29 delivery year auction, according to its own fact sheet, with all new resources to reach commercial operation by 1 June 2032. PJM missed its reserve margin target in each of its last two base capacity auctions. Its footprint covers 13 Mid-Atlantic and Midwest states and the District of Columbia.

The same question is open in neighbouring markets and in Congress. MISO has asked FERC to fast-track studies for loads above 200 MW that bring their own generation, as Parallax Nexus reported on 5 October, and a Senate permitting package introduced on 30 September would bar utilities from charging other customers for a data centre load above 20 MW. DOE's filing pushes the principle through an existing docket rather than new law.

The pledge doing the argument's work

DOE anchored its reasoning in the White House Ratepayer Protection Pledge, under which large electric loads rather than households or other business customers fund the generation and related infrastructure their projects require. Utilities operating in PJM's territory that have signed the voluntary pledge include American Electric Power, AES, CenterPoint Energy, Dominion Energy, Exelon, FirstEnergy and PPL. Utility Dive, which reported the filing on 7 October, said it appears to be the first statement of position DOE has filed at FERC in at least five years.

On the substance, the department echoed the regulator.

DOE shares the Commission's concerns that PJM's proposed [reliability backstop procurement] cost allocation model may be unjust and unreasonable

— US Department of Energy, statement of position filed at FERC, 7 October 2026

Its fix is administrative: allocate costs using updated load forecasts, and track each large load project well enough to know whether it entered service, slipped, shrank or was cancelled. Without that data, DOE argued, PJM cannot avoid double counting, lower the procurement target when forecast load fails to appear, or assign demand growth to the right zone and load-serving entity. The department also said PJM's tariff may omit large loads already sitting in the baseline forecast.

PJM is not waiting for February

Jeffrey Shields, a spokesman for PJM, told Utility Dive on 8 October that the grid operator intends to file a revised proposal by 29 October rather than sit through the hearing, and will hold a special Members Committee meeting on 22 October to consult members on its contents. FERC's order left that door open, telling PJM it could propose its own fixes using the guidance in the order.

A statement of position carries no binding force. FERC decides, and the department is one voice in a contested docket. What makes this one worth logging is the alignment: the federal energy department, the federal energy regulator and a bipartisan group of senators have landed on the same test, whether the customer causing new generation to be built is the customer billed for it. Whether PJM's 29 October filing adopts FERC's guidance in full is not known.

What happens next?

  • PJM holds a special Members Committee meeting on 22 October 2026 to consult members on its revised filing.
  • PJM intends to submit a revised Reliability Backstop Procurement proposal to FERC by 29 October 2026.
  • If PJM does not file or FERC rejects the revision, the suspended plan takes effect on 28 February 2027 subject to refund, after a hearing process running through February.
  • FERC's separate decision on PJM's Interim Resource Adequacy Service filing remains pending.

Sources & references

  1. 01Statement of Position of the United States Department of Energy, Docket ER26-3380 — FERC eLibraryprimaryFiled 7 October 2026; accession number 20261007-5181
  2. 02Order Accepting and Suspending PJM Reliability Backstop Procurement, Docket ER26-3380 — FERC eLibraryprimaryIssued 29 September 2026; effective date suspended to 28 February 2027
  3. 03DOE presses PJM on ratepayer protections from large load costs — Utility DivenewsPublished 7 October 2026, updated 8 October with PJM spokesman Jeffrey Shields's comments
  4. 04Reliability Backstop Procurement fact sheet — PJM InterconnectioncompanyProcurement target of about 6.8 GW
  5. 05FERC Accepts PJM Proposed Reliability Backstop Procurement, But Suspends It for Five Months — American Public Power AssociationreportPJM's statement on the order and the 1 June 2032 commercial operation deadline
  6. 06Ratepayer Protection Pledge — The White HouseprimaryVoluntary pledge cited by DOE in its filing
Published 9 October 2026 · Updated 9 October 2026 · Report a correction · How we use AI
inLinkedIn𝕏Post

More from Energy

View all
Energy

EQT Buys Range Resources to Pass 9 Bcfe a Day in Appalachia

EQT and Range Resources agreed on 26 October 2026 to an all-stock merger at 0.987 EQT shares per Range share, leaving EQT holders with about 73 per cent of a company producing more than 9 Bcfe a day. Closing is expected in the first quarter of 2027, subject to regulatory clearances and shareholder votes.

3 min read
Energy

Amazon Funds a 960MW Reactor Study at an Indiana Coal Site

AEP agreed on 19 October 2026 to study 960 megawatts of small modular reactors at a retired Indiana coal site, with Amazon funding development and contracting for the power. There is no final investment decision, no disclosed cost and no in-service date.

3 min read
Energy

NERC Grid Rules Clear Ballot With 36-Month Recorder Delay

NERC announced on 15 October 2026 that Project 2026-02, a package of three new reliability standards for data centres, AI facilities and cryptocurrency mines, had passed its final stakeholder ballot. It now goes to NERC's Board of Trustees and then to FERC, which ordered the standards filed by 31 December 2026.

3 min read